World Trade Center

Resorts North Tower

 

Consolidated Edison

Philadelphia Convention Center

 

Atlantic City Convention Center

Hangar 55, Newark, NJ Airport

   

 

WORLD TRADE CENTER
Project:
Clean up the World Trade Center site.

Challenges:
The challenges at the World Trade Center were the extreme conditions, both emotional and physical.

The emotional challenge was to overcome the shock, the sense of mass destruction, and the loss of life. The knowledge that, in the first weeks, we were there not to just clean up, but to search for victims.

The physical challenge was the sheer magnitude of the project and its components. A beam 30 feet long and 8 feet wide weighed between 60 and 80 tons—steel so heavy it broke grapples and twisted booms. With ground temperatures reaching in excess of 1,200°F, steel beams were pulled out of the wreckage glowing red.

Solutions:
On the emergency list for the City of New York, Mazzocchi's team arrived at the site with essential machinery (including the EX550 LRD). Our workers at the site during the first week said they overcame the shock and the sight of the victims by focusing on the work, on the necessary job that had to be done.

Mazzocchi had other responsibilities away from Ground Zero. We used our fleet of trucks to haul the twisted metal to the Hudson River, where it was immediately shipped to the Fish Kills site. There, Mazzocchi assisted in strategically sorting the material for federal officers' final inspection.

One supervisor said the most remarkable thing about the whole job was the unity during the first few days, with the Red Cross, police, firemen, emergency personnel, construction workers and people on the street all coming together to help. This spirit of unity continued throughout the project as contractors worked together—under the overall supervision of the New York City Department of Design and Construction—to get the job done.

Multiple contractors working together was one essential element in overcoming challenges. Another was just plain hard work. A second Mazzocchi supervisor said the hardest part for him was being away from his family for six months, as he worked 12-to 15-hour shifts six or seven days a week.

On the purely mechanical side, we had the back-up machinery to move in if any of our equipment on site was damaged by the extreme conditions. We had the ability to repair or replace machinery immediately, resulting in little or no downtime.

Result:
We worked continually at the site from September 11 to the beginning of March 2002. But the real result of the project and of the entire September 11 crisis was a greater unity in America and a greater sense of needing to work together. Mazzocchi Wrecking is proud to have been a part of that result.

(return to top)



Click here to view more photos

RESORTS NORTH TOWER
Project:
Surgical demolition of 12 story building next to active casino in October 2002. Mazzocchi worked around the clock to meet Perini's tight schedule.
(return to top)

 

 

 



Click here to view more photos

CONSOLIDATED EDISON
Project:
Demolish two power plants, two support structures, and an 11-story office building at ConEd’s Waterside complex, which covers five city blocks between First Avenue and the FDR Drive in Manhattan. Generating both steam and electricity, the Waterside complex used to serve one-fourth of Manhattan and is one of the largest such complexes on the East Coast.

As of March, 2002, we have already demolished the office building and were commencing work on the support structures. The final phase would be to remove the power plants themselves.

Challenges:
The office building was situated right next to the intake vents for the Queens-Midtown Tunnel, and the tunnel itself ran directly beneath the building’s foundation. The support structures, a switch house and a frequency house, contain significant amounts of asbestos—even in the caulking around the window frames. These structures also present a large gymnasium-like area, so when the roof comes off, the walls may be unstable.

The power plants themselves are 17 stories high, with stacks that extend another 300 feet beyond that. With immense boilers and turbines, this job is difficult in part for its size and because the walls of the plant come right up to the sidewalk, therefore requiring a large amount of hand demolition. The supporting steel beams that span the whole power house are eight feet high, and the flanges are between five and six inches thick. The challenge is to take the plant down in a controlled manner.

Solutions:
In demolishing the office building, we took special steps to minimize both dust and vibrations. In taking down the support structures, we will take extra safety precautions against working in a large unsupported area.

The generators themselves are so large that, after we have removed the PCBs and drained the oil from the tanks, we will take down the buildings around them and then use machine power to break them up and pull them out. Because we can perform all the necessary services and own our machines, we can provide a cost-effective, turnkey solution.

Result:
Because we have the right people and the right machines, we expect to complete the project safely and effectively.
(return to top)


 

Philadelphia Convention center
Project:
Demolish and clear the site to make room for a New Philadelphia area hospital. The center was host to such historical notables as the Beatles in 1967, the Philadelphia ‘76ers and numerous conventions. Start date was February 28, 2005. Completion and new construction is slated for January 2006.

Challenges:
The Convention Center had a 200’ lateral center height and a vast interior expanse. Implosion was not an option due to its location near The Children’s Hospital and Penn University. Dust, noise and vibration had to be kept to a minimum. Pedestrian traffic could not be interrupted and the main roads and railroad that surrounded the Center could not be closed.

Solutions:
A unique “hinging” process was thoroughly planned onsite by the supervisor, operators and crew of Mazzocchi Wrecking. The Mazzocchi LRD 750 was utilized to safely “snip” and dismantles the vast center span supports of the building. The 200’ high stage and the main entry foyer were then dismantled. All the time being cognizant of historical architectural features that were salvaged at the request of Penn University.

The Mazzocchi LRD 750 is a custom piece of equipment. It has a 160’ (48.8 meter) boom, a near-tool mounted water canon to reduce dust and extinguish potential fire and a mounted video camera to monitor demolition details from the ground, safely. The Mazzocchi LRD 750 utilizes several tools, each tool specific for a particular project.

Large pieces of steel removed by the LRD were then cut and sorted along with limestone and recyclables. Debris was removed from the site via Mazzocchi containers that flowed through the site on a scheduled basis to assure a non-obstructed safe and productive work environment.

Site Assets:

  • 1 Supervisor
  • 4 Operators
  • 2 Laborers (additional personnel as needed)
  • Mazzocchi LRD 750 (with 160 boom and “snip/shear” tool attachment)
  • Mazzocchi EX 600 (large debris mover)
  • Mazzocchi 470 (handles a magnitude of steel.)

  • (return to top)

ATLANTIC CITY CONVENTION CENTER
Project:
Remove asbestos-containing panels from the ceiling of the Atlantic City Convention Center—the site of the annual Miss America Pageant.

Challenges:
The roof was formed of rainbow-shaped trusses and was 130 feet high at the peak. And because of the interstitial spaces between the ceiling and the roof, workers had to climb the trusses, making working conditions difficult. A further difficulty was presented by the need to work inside the air chamber of the convention center’s large pipe organ.

Solution:
The first step was to design and install scaffolding that would traverse the long hall, which was finally done in 30-foot squares, each contained in polyurethane. On top of that, we erected scaffolding which would allow our workers to do the abatement work on the ceiling. Then, we took elaborate measures, including harnessing and close monitoring, to ensure the safety of the workers.

Result:
Because we bring a wide range of technical expertise to every project, we completed this sophisticated and challenging job without incident.
(return to top)



Click here to view more photos

HANGAR 55, NEWARK AIRPORT
Project:
Demolish the central portion of a large aircraft hangar and remove asbestos from the coating to the skin covering the entire building.

Challenge:
Continental Airlines needed to remove the central portion of the hangar so it could build it higher to accommodate widebody jets, but the other two sections of the building were still in operation. The central portion of the building had large and intermediate steel trusses which had to be cut.

Solution:
To minimize the need for lead abatement, which is always present when steel is being cut, we had to plan our effort well in advance. When that portion of the project was completed, we installed new steel girts and longer rods to accommodate the central portion’s new skin.

So workers could remove the quarter- to half-inch-thick asbestos-containing coating, we had to construct a scaffold covering the entire outside of the building.

Result:
Because we always plan carefully to maximize efficiency, we completed the project on time and on budget.
(return to top)


Click here to view more photos