HANGAR
55, NEWARK AIRPORT
Project:
Demolish the central portion of a large aircraft hangar
and remove asbestos from the coating to the skin covering
the entire building.
Challenge:
Continental Airlines needed to remove the central portion
of the hangar so it could build it higher to accommodate
widebody jets, but the other two sections of the building
were still in operation. The central portion of the
building had large and intermediate steel trusses which
had to be cut.
Solution:
To minimize the need for lead abatement, which is always
present when steel is being cut, we had to plan our
effort well in advance. When that portion of the project
was completed, we installed new steel girts and longer
rods to accommodate the central portions new skin.
So
workers could remove the quarter- to half-inch-thick
asbestos-containing coating, we had to construct a scaffold
covering the entire outside of the building.
Result:
Because we always plan carefully to maximize efficiency,
we completed the project on time and on budget.